Promised vs actual
Five projects, only the dates and dollars the record states.
Slip in days and budget variance stay not stated where the source gives a month, a phrase such as “about two months,” or a grant total on both sides.
Projects
| Project | Status | Promised | Revised | Actual | Slip (days) | Budget variance | Source |
|---|---|---|---|---|---|---|---|
| Relocated Fire Station 8 | Completed late | 2026-05 | not stated | 2026-07-21 | not stated | not stated | 26-1045 |
| New Fire Station 32 | Slipped | 2026-04 | 2026-09 | not stated | not stated | not stated | 26-1045 |
| Police Training and Academy Facility | Slipped | 2025-12 | 2026-12 | not stated | not stated | not stated | 26-1045 |
| Coyote Creek Flood Protection Project (Phase 2) | On track | 2028-12 | not stated | not stated | not stated | not stated | 26-1099 |
| Pure Water Silicon Valley (full-scale facility) | On track | 2035 | not stated | not stated | not stated | not stated | 26-1100 |
The one dollar figure
Pure Water stores $3,295,950 as both the promised and actual amount. That is the grant total already cited ($1,092,000 and $2,203,950). The record does not state a construction variance, so the variance cell stays not stated. Source: 26-1100.
— J Gonzales